2. Use the beam as a reference to mark
where the floor joist will be placed.
The 2x4 floor joist, when installed,
will be aligned with the wall studs.
Step 14 Install Loft Joist Headers & 2x6 Loft Beams
4. To allow access to the loft area, a 16' long building requires cutting (10) ten 7' long 2x4s to
a length of 6'.
5. Install the rear 2x6 beam,
72" from the 2x4 joist header boards, with the 'X' marks on the
beam facing the back wall. You can use a 2x4-6' board as a gauge to properly space the beam.
Refer to Step 15 to see how the loft floor joist will be installed.
Place the notch under the top plate and support the beam by cutting a pre-cut wall stud and
placing under the beam. Further secure the beam with a 3" wood screw through the top of the
wall plate and toenail to the bottom plate and beam with 10d sinkers.
2x6 Beam
2x4 Cut to Length
6. Repeat to Install the other beam with the 'X' marks on the beam facing the front wall.
When the front beam is installed there will be 56" between the beams
1. Install (2) two 68-1/2" long 2x4s on the back wall to support the floor joist. Install
the 2x4s flush with the top of the 2x4 wall plate. Secure to wall studs with 10d sinkers.
68-1/2" Long 2x4
3. Repeat to install joist header support boards on the front wall.
Back Wall